Structure name | Minami-ohashi Bridge |
---|---|
Structure type | PC 3-span continuous box girder bridge |
Structural factors | Length of bridge 283.8m、 Span length 2×3@45.2m |
Client | Sapporo city |
Contractor | Taisei Co. |
Location | Sapporo city |
Route name | 1.3.9 Minami 9-jo toori |
Completion date | 1963 |
Overview | The features of this bridge include applying the Leonhardt method for prestressing in the principal direction, adopting the fan anchorage method of anchoring so that the strands are dispersed in a fan shape at the end of the girder and fixed to the concrete. This bridge was the first application of the large fan anchorage method (2800t×2) in Japan. The Leoba method was adopted for the transverse prestressing. Part of the deck slab overhang has a rib structure with a length of 4.4 meters. In consideration of the landscape, the side slope of the pier structure is the same as the slope of the web in the superstructure. |