Structure name | Boukei Bridge |
---|---|
Structure type | PC2 continuous span large decentering Cable Truss midair slab bridge |
Structural factors | Length of bridge 57.3m Span length 23.0+33.2m |
Client | Hokkaido morimati |
Designer | Civil Engineering Services co.ltd. |
Contractor | Joint-venture group:DPS Bridge Works Co.,Ltd・Sumitomo Mitsui Construction Co., Ltd |
Location | mori |
Completion date | 2011 |
Overview | This bridge is a pedestrian bridge over the Shimazaki River between the left bank park and right bank park. The bridge features economic improvement by reduction in the weight of the superstructure due to the introduction of prestress and reduction of the girder height due to eccentric arrangement of the outside cable following the bending moment. In addition, this bridge possesses a finback form that covers the eccentric portion on the intermediate fulcrum with concrete, so that the bridge can also be considered a landmark of the park. |